89 Kilometres of the Ramganjmandi–Bhopal Line Are Complete in Bhopal Division
West Central Railway has completed 89 kilometres of the 111-kilometre Ramganjmandi–Bhopal line section within Bhopal division. The wider project spans five districts in Madhya Pradesh and Rajasthan; the remaining 22-kilometre Narsinghgarh–Kurawar section is targeted for completion by December 2026.
- The reported 89-kilometre completion is within Bhopal division, while the three-hour saving is an expectation for the completed route.
- The 89 completed kilometres include sections from Nishatpura D-Cabin to Kurawar, Biaora–Rajgarh–Sonkatch and Sonkatch–Narsinghgarh.
- Three sections totalling 52.50 kilometres were commissioned in 2026.
- Once complete, the route is expected to be about 42 kilometres shorter than the existing route via Biaora–Jhalawar, saving about three hours of travel time.
NYOOOZ Bhopal Desk · Based on a news report
Did this help you understand the story?