Keralam's First Automatic Signalling System to Be Installed on 102-km Rail Corridor
The Ernakulam Junction-Vallathol Nagar rail corridor will be upgraded with Keralam's first automatic signalling system as part of a ₹156-crore project. This upgrade aims to triple the track capacity and reduce waiting times for trains, enhancing overall efficiency.
- The new signalling system will significantly improve train scheduling and capacity on the Ernakulam-Vallathol Nagar corridor.
- The project will cost ₹156 crore and is expected to be completed by June 2024.
- Currently, 45 km of cables have been laid, with ₹68 crore worth of work already completed.
- The automatic signalling system will allow three trains to operate simultaneously between stations, improving scheduling and reducing delays.