Kochi survey flags sewage-treatment gaps in four central divisions
Representative visualA Kerala Water Authority survey in Perumanoor, Kadavanthra, Panampilly Nagar and Girinagar found that septic tanks at many establishments were not adequately treating sewage. The areas generate 2.8 million litres of sewage daily, while planned pipeline and treatment-plant work has faced tender delays and technical hurdles.
- The reported treatment gaps and project delays concern four surveyed central Kochi divisions, not the entire city.
- The survey covered 31,283 people and households, hostels, apartments, commercial complexes and other establishments.
- The planned project includes a 27.5-kilometre pipeline network, a 5-MLD treatment plant and a separate 17-kilometre network.
- The 17-kilometre network was held up by legal disputes in the tender process; no bidder qualified in technical evaluation for the treatment plant.
NYOOOZ Kochi Desk · Based on a news report