Consumer commission orders developer to refund Rs 86 lakh to Mumbai homebuyer after 10-year wait
A Mumbai resident who booked a flat in Panvel for Rs 50 lakh in 2015 has been awarded a refund of Rs 86.37 lakh by a consumer commission after nearly a decade of waiting for possession. The commission ruled against the developer for failing to meet the terms of the agreement, although additional claims for interest and amenities were denied.
- The ruling highlights the legal recourse available to homebuyers facing delays in property possession.
- The homebuyer booked the flat for Rs 50 lakh in 2015.
- The consumer commission ordered a refund of Rs 86.37 lakh with 9% interest.
- The developer did not provide satisfactory explanations for the delays.
NYOOOZ Mumbai Desk · Based on a news report
Did this help you understand the story?