Uttarakhand rescue: After a week chances of life bleak, rescue at war footing

  • | Monday | 15th February, 2021

In the week since the flash flood in Uttarakhand’s Chamoli district, two tunnels of an NTPC hydro-power project in Tapovan area have been at the centre of rescue operations. The initial target was to clean a 180-metre area of slush to rescue 34 workers feared trapped there. On Sunday, five bodies were recovered from one of the tunnels.

In the week since the flash flood in Uttarakhand’s Chamoli district, two tunnels of an NTPC hydro-power project in Tapovan area have been at the centre of rescue operations. The initial target was to clean a 180-metre area of slush to rescue 34 workers feared trapped there. On Sunday, five bodies were recovered from one of the tunnels.

Revisiting the painstaking, day-to-day progress in the operation, the changing strategies:

February 8

The rescue operation inside the intake tunnel, started after the February 7 flash flood, was halted for a few hours following a rise in the Dhauli Ganga river. It resumed at 5 am on Monday. The slush was cleared up to only 90 metres after a day-long exercise.

February 9

After removal of slush with rudimentary equipment like excavators, an aerial survey was done by a helicopter-bound Laser with Electromagnetic Pulse Imager for analysis of the density inside the intake tunnel. A drone with cameras was also sent inside the tunnel up to 120 metres, but failed to show human presence in that stretch. This day, NDRF and ITBP personnel were able to only reach up to 90 metres— as they removed the slush, more muck kept coming out. Army men attempted to launch a search near the barrage in Dhauli Ganga—a site where more than a hundred people are feared missing—but called it off after finding the surface unsuitable for movement. The rescue appeared more organised when a joint operational centre was set up and layout of the tunnel was displayed in public.

Rescue operations on at the Tapovan hydel project in Chamoli district, Uttarakhand. (Express file photo by Gajendra Yadav)

February 10

Rescue teams changed strategy after discovering that workers may be trapped in another silt filtration tunnel (SFT), located 12 metres below the intake tunnel. It was decided to start drilling 72 metres from the opening of the first tunnel. This was done so that lights with cameras could be lowered into the SFT. Two more excavators were deployed to speed up the removal of slush. A helpdesk was set up for relatives of those people feared trapped.

The operation was suspended following a rise in river water flow, but resumed after an hour. Around 80 metres of slush was cleared in the intake tunnel. Drilling into SFT started at 3 am but was stopped due to sludge at a depth of 6 metres.

February 12

A fresh attempt was made drill into the SFT at a distance of 75 metres. Teams managed to achieved drilling to more than 10 metres by evening.

February 13

Drilling inside SFT was completed up to a depth of 12 metres. With little space for lowering a camera, another heavy machine was pressed into service to increase the diameter of the drilled area up to 30 cm and develop a borewell. But the lowering of camera failaed again due to the pressure of slush. The borewell was plugged and removal of slush from the intake tunnel resumed again late night.


If You Like This Story, Support NYOOOZ

NYOOOZ SUPPORTER

NYOOOZ FRIEND

Your support to NYOOOZ will help us to continue create and publish news for and from smaller cities, which also need equal voice as much as citizens living in bigger cities have through mainstream media organizations.


Stay updated with all the Dehradun Latest News headlines here. For more exclusive & live news updates from all around India, stay connected with NYOOOZ.

Related Articles