30% of Pimpri-Swargate Metro route construction in PCMC limits complete

  • By TOI
  • | Tuesday | 10th July, 2018

PIMPRI CHINCHWAD: The Maharashtra Metro Rail Corporation has completed 30% of the construction of the Pimpri-Swargate route in Pimpri Chinchwad.Work on the route in PCMC limits had begun in June 2017, as most of the route is aligned along the middle of the Pune-Mumbai highway. We have also deployed a quick response team to solve traffic congestion,” he added.“We laid foundations for 159 pillars in PCMC limits, and also completed piers for 114 pillars. “It is a 10-lane highway and we are using the 2-3 lanes in the middle, which is not affecting traffic. Also, the construction of 50 pillars with pier caps has been completed,” Birhade said. Also, the construction of the station at Sant Tukaramnagar has begun,” he added.