Noida Authority outlines upgrades for Botanical Garden bus terminal
Representative visualThe Noida Authority announced plans to renovate the Botanical Garden bus terminal in Sector 38A, adding lighting, passenger information displays and electric-bus charging facilities. The project also includes civil works such as bus platforms and a waiting area; officials say completion is expected 18 months after work begins.
- The announced work covers both terminal facilities and electric-bus infrastructure, but its completion period begins only after construction starts.
- The terminal connects Noida with Greater Noida, Greater Noida West, Jewar and Delhi, and serves around 270,000 commuters daily, officials said.
- Plans include four 240-kilowatt fast-charging stations and 26 bus platforms.
- A ₹9.45 crore tender for electrical work was issued on November 19; it is separate from the ₹20 crore allocated for civil works.
NYOOOZ Noida Desk · Based on a news report
Did this help you understand the story?