Pune's Swargate-Katraj Metro extension set to start tunnelling in January with arrival of first tunnel boring machine
Representative visualThe tunnelling for the Swargate-Katraj Metro extension is scheduled to commence in January 2026, following the arrival of the first tunnel boring machine. This 5.46-kilometer underground stretch aims to enhance connectivity in southern Pune and alleviate traffic congestion.
- The new Metro extension is expected to significantly improve public transport in southern Pune.
- The Swargate-Katraj Metro extension will be 5.46 kilometers long and entirely underground.
- Four tunnel boring machines will be used, with two operating from each end of the route.
- Excavation is targeted at around 10 meters per day per machine, at a depth of approximately 28 meters.