9-month deadline to complete STPs

Bengaluru | Thursday | 12th December, 2019

Summary:

Justice Adarsh Kumar Goel expressed displeasure over the delay in building STPs and pulled up BWSSB chairman Tushar Girinath for seeking two more years to build STPs, which, experts had said, could be done in nine months. The principal bench of the NGT pulled up officers of BBMP, BWSSB and KSPCB, saying it is inclined to file criminal cases against them for dereliction of duty. The state government agencies submitted that they are installing CCTV cameras, deweeding and desilting the lakes and clearing encroachments. The agencies said they will be unable to complete the installations of STPs by September 2020 and sought a few more weeks’ time to come up with corrective measures. The NGT noted that it is a “colossal waste of money” as treated water enters the sewage plant and mixes with untreated water and then treated again..