Coimbatore Corporation fixes monthly targets for contractors

Coimbatore | Thursday | 8th October, 2020

Summary:

Corporation Commissioner held a meeting a couple of days ago to review the progress in model road, lake development, multi-level car parking and other Smart Cities Mission works.

.

In an effort aimed at expediting the progress of projects taken up under the Smart Cities Mission, the Coimbatore Corporation has fixed fortnightly and monthly targets for contractors.

Corporation Commissioner P.

Kumaravel Pandian held a meeting a couple of days ago with engineers, project management consultants and contractors to review the progress in model road, lake development, multi-level car parking and other Smart Cities Mission works.

At the meeting, he asked the contractors to divide the projects into small components to fix targets for each of those components and fortnightly and monthly targets and stick to those to complete the project in time, said Deputy Commissioner S.

Madhuranthagi.

The Commissioner had asked the contractors to complete the model road work, taken up on D.B.

Road, R.S.

Puram, by December 2020.

Likewise, he had asked the contractor executing the multi-level car parking project, again on D.B.

Road, by January 2021.