Petrol pump a hurdle too steep for Iffco underpass

Gurgaon | Tuesday | 10th July, 2018

Summary:

The underpass is 97% ready, except for the petrol pump area.”Meanwhile, officials at Gawar Construction said with the petrol pump relocation stalled, drains haven’t been connected properly.“Monsoon will be a big problem for the petrol pump and underpass, as drains in the area haven’t been linked with the main outlet,” said a Gawar official.The alternative plot allotted to the fuel station was originally earmarked for a taxi stand in the Master Plan. Till a new site is allotted by Huda, work on this site can’t resume. It reminded the state government that the latter had assured NHAI could carry out the project without a hurdle while handing it over. “Under contract conditions, any further delay in handing over the site would result in financial contractual implications for NHAI,” the letter states. The owner of a neighbouring building — Ameya One — filed a petition before the district and sessions court on February 7, questioning Huda’s change of land use..