Urbanrise Sets Yet Another Record in the Real Estate Space by completing one floor using MFE Formwork in just 2.5 days

Hyderabad | Friday | 11th November, 2022

Summary:

HYDERABAD, India, Nov.

11, 2022 /PRNewswire/ -- Urbanrise have been at the forefront of creating new records in the realty space.

The technical team of Urbranrise"s project, "The Happening heights", has carved yet another milestone by completing the construction of a slab in a span of a mere 2.5 days.

Average construction cycle per floor of Residential Building using MFE Formwork (earlier known as MIVAN Formwork) is usually 8 to 12 days, which includes activities such as fixing of Steel, erection of shuttering, MEP services and pouring of concrete, among several others.

Defying established standards, the technical team undertook the mammoth task and completed one floor of 21,500 sq.

ft.

of Shuttering area in just 2.5 days starting from 6 am on 5th Nov to 6 pm on 7th Nov-22.

Under the leadership of Mr.

Koti Sai, General Manager-Projects,"The technical team took the challenge to make 2.5 Day Cycle, a reality.