Two years on, no smart city project complete

Ludhiana | Friday | 20th April, 2018

Summary:

Tenders for retrofitting of the Sarabha Nagar Market Project (cost Rs 14.89 crore) and Development of Malhar stretch (cost Rs 22.75 crore) have been floated. Rooftop solar panels project (cost Rs 2.55crore) on existing buildings will be completed by April 30. According to information, combined tenders for retrofitting of the Sarabha Nagar Market Project (cost Rs 14.89 crore) and Development of Malhar stretch as smart road (cost Rs 22.75 crore) have been floated. The DPRs for the Smart Road, Phase II, (cost of Rs 35 crore), construction of cycle tracks (cost Rs 20 crore), junction improvement and smart foot overbridges (cost Rs 21 crore) yet be submitted. The DPR of Integrated Command Control Centre ( Rs 32.50 crore) and Digital Library (Rs Rs crore) will be submitted by May 15..