Road restoration project works in Guntur running behind schedule

Vijayawada | Thursday | 21st June, 2018

Summary:

However, we are going ahead with additional teams to reach the target set by the commissioner,” Shapoorji Pallonji project director Ramesh told TOI. Officials said 5km of road works have to be taken up each day to meet the target and that it is a very daunting task. However, the commissioner shot down all such requests in view hundreds of public complaints. They believe construction of 2km of works can be taken up everyday in the current scenario.Interestingly, Shapoorji Pallonji could dig just 2.5km road per day (on an average) to lay the UGD pipelines in the last one year. “While digging the road in itself is a difficult task, re-construction is an even more challenging task,” said an engineer of the public health department.“It is true that it is a herculean task..