WR-BMC fight delays ROB at Mahalaxmi

Mumbai | Thursday | 6th December, 2018

Summary:

"However, BMC officials say that the railways has to construct the ROB portion over the railway line. There has been no such request with the civic agencies that we should undertake construction above our portion. The official said that the railway sent a response recently with a clause that "The portion of ROB over railway shall be executed by the MCGM under the supervision of railway engineer. We ourselves construct and maintain railway bridges across the zones whose track kilometres is thousands and areas. "In July this year too, there was a similar dispute between the two authorities over who would reconstruct Delisle bridge..