After 3 years, a 300-metre flyover in Vizag rural is still in the making

Visakhapatnam | Wednesday | 23rd December, 2015

Summary:

Till date, the roads and buildings department has completed building 18 pillars for the Rs 18 crore flyover project and connected just five pillars with a road. Spread over a length of only 300 metres, the construction of the flyover is moving at snail's pace. " He said, "If they can't build the flyover, they should at least repair the road below it. " "On an average, we have at least 100 trains including passenger as well as goods trains passing on this route. R&B department sources said shortage of sand, land acquisition issues near the flyover as well as delay by the contractor were the reasons for the delay in completing the project..